Update as of 6/25/2026
Sidewalks and aprons on Bubier Road, Gerry Street, Atlantic Avenue between Gerry Street and Bubier Road, and Wyman Road that are currently gravel are scheduled to be paved on Friday, June 26, 2026 (base course only). Thank you for your patience as we are able to complete this work earlier than planned.
Two week schedule posted below.
Additional updates will be posted as available for future work and final paving dates for roadway and sidewalks.
NOTE: Final paving of sidewalks will occur following final roadway paving operations. As needed, the contractor will be applying loam and seed following final sidewalk paving.